top of page

ADU Building

Our team has partnered with local builders to help our clients design and build high-quality ADUs that add value to their properties. We guide clients through every step—from planning and permitting to construction and completion—ensuring a smooth process and beautiful results. Whether you’re looking to create extra income or house family members, we have the tools to bring your ADU vision to life.

Plans for ADU built in Fallbrook, California

#1 Planning & Design

July 6, 2024

Every great ADU starts with a clear vision. During this stage, we finalize floor plans, materials, and design details to ensure the project meets your needs and budget.

#2 Site Preparation

September 4, 2024

The property is cleared, graded, and prepared for construction. Utilities and access points are planned to ensure a seamless process.

Site grading for ADU built in Fallbrook, California
Plumbing for ADU built in Fallbrook, California

#3 Foundation Work

September 12, 2024

Plumbing groundwork is completed, and the foundation is poured. This step provides the structural base that supports the entire ADU.

#4 Framing & Structure

October 2, 2024

Walls, floors, and roof framing go up, bringing the design to life. You’ll start to see the true size and layout of your new space take shape.

Framing for ADU built in Fallbrook, California
Framing for ADU built in Fallbrook, California

#5 Plumbing, Electrical, & HVAC

October 3, 2024

All essential systems are installed and tested. This includes running pipes, wiring, and ductwork to ensure your ADU functions efficiently and safely.

#6 Doors & Windows

October 18, 2024

Exterior doors and windows are installed for security, energy efficiency, and curb appeal. This step seals the structure from the elements and adds character.

Newly installed doors and windows on ADU built in Fallbrook, California
Exterior of ADU being built in Fallbrook, California

#7 Exterior Work

October 31,2024

The exterior walls are wrapped, waterproofed, and prepared for stucco. These steps protect the home from moisture and improve long-term durability.

#8 Roofing & Tile Work

November 1, 2024

Roofing paper is laid, and tiles are placed. Once finished, the ADU is fully protected from the weather, so interior work can begin.

Roof tiles being placed on ADU built in Fallbrook, California
Insulation and drywall being installed in ADU built in Fallbrook, California

#9 Insulation & Drywall

November 2, 2024

Insulation is placed in walls and ceilings to regulate temperature and sound. Drywall installation follows, creating smooth, paint-ready surfaces.

#10 Stucco

November 4, 2024

Stucco is applied in multiple coats to achieve a clean, durable exterior finish. This step gives the ADU its signature look and lasting weather protection.

Stucco added to exterior of ADU built in Fallbrook, California
Septic tank being installed for ADU built in Fallbrook, California

#11 Septic Tank

November 19, 2024

The septic tank is installed to handle wastewater safely and efficiently. This step ensures your ADU meets all environmental and health standards.

#12 Interior Finishes

November 19, 2024

Flooring, cabinets, countertops, paint, and hardware are picked out to bring personality to the space. Each room begins to reflect the chosen design style and finishes.

Interior finishes selected for ADU built in Fallbrook, California
Leach lines installed in ADU built in Fallbrook, California

#13 Leach Lines

November 27, 2024

Leach lines are installed and connected to the septic system for proper drainage. This phase is essential for maintaining long-term system function.

#14 Cabinets & Countertops

December 13, 2024

Custom cabinetry and countertops installed. The kitchen and bathrooms start to take shape with the finishes selected.

New cabinets and countertops installed in ADU built in Fallbrook, California
Bathroom installation in ADU built in Fallbrook, California

#15 Bathrooms

December 16, 2024

Vanities, fixtures, tile, and mirrors are installed to complete the bathrooms. Each detail is decided on by the client.

#16 Backsplash

December 18, 2024

The backsplash is installed to fill the wall between the countertops and cabinets

Backsplash installation in ADU built in Fallbrook, California
New LVP flooring installed in ADU built in Fallbrook, California

#17 Flooring

January 2, 2025

​Luxury vinyl plank, tile, or hardwood flooring is installed throughout. This step ties the home together and enhances the overall look and feel.

#18 Driveway

January 22, 2025

Concrete is poured and finished for the driveway and walkways. This provides smooth, durable access to the ADU while enhancing curb appeal.

Driveway poured for ADU built in Fallbrook, California
Fencing installed around ADU built in Fallbrook, California

#19 Fencing

January 30, 2025

Perimeter and privacy fencing are built to define the property and mark property lines.

#20 Finished ADU

February 12, 2025

The ADU is complete, cleaned, and ready for move-in. Every detail comes together to create a high-quality living space built custom to you.

Finished modern kitchen in ADU built in Fallbrook, California

Build Yours

Not sure where to begin? Our team simplifies the ADU process so you can move forward with clarity, confidence, and the right experts in place.